WEBVTT FILE

1
00:00:00.010 --> 00:00:04.030


2
00:00:04.050 --> 00:00:08.090


3
00:00:08.110 --> 00:00:12.160


4
00:00:12.180 --> 00:00:16.260


5
00:00:16.280 --> 00:00:20.300


6
00:00:20.320 --> 00:00:24.360
Art Azarbarzin: In December 2009, we had our

7
00:00:24.380 --> 00:00:28.390
CDR and shortly after that we started the manufacturing process

8
00:00:28.410 --> 00:00:32.420
for all the components of GPM.

9
00:00:32.440 --> 00:00:36.440
After about a year and a half, we started putting the spacecraft structure

10
00:00:36.460 --> 00:00:40.500
together and went through the qualification of the structure and,

11
00:00:40.520 --> 00:00:44.570
the step after that was installing the harness.

12
00:00:44.590 --> 00:00:48.720
The harness for a spacecraft is a component which

13
00:00:48.740 --> 00:00:52.810
basically all the wires that we put on the spacecraft that connects all the boxes

14
00:00:52.830 --> 00:00:56.860
together with the connections at each end.

15
00:00:56.880 --> 00:01:00.900


16
00:01:00.920 --> 00:01:04.940
Candace Carlisle: We started the integration of the observatory with the

17
00:01:04.960 --> 00:01:08.960
delivery of the two instruments: the GPM Microwave Imager

18
00:01:08.980 --> 00:01:13.000
and the Dual-frequency Precipitation Radar in early 2012.

19
00:01:13.020 --> 00:01:17.020
These were then integrated onto the spacecraft,

20
00:01:17.040 --> 00:01:21.030
and we checked everything out to make sure everything works

21
00:01:21.050 --> 00:01:25.100
culminating with a Comprehensive Performance Test

22
00:01:25.120 --> 00:01:29.150
in October of 2012.

23
00:01:29.170 --> 00:01:33.230
Before we launch any spacecraft we do a very

24
00:01:33.250 --> 00:01:37.270
lengthy and detailed set of tests to make sure

25
00:01:37.290 --> 00:01:41.310
that the spacecraft is going to survive all the environments that

26
00:01:41.330 --> 00:01:45.340
it's going to see during the launch and on orbit.

27
00:01:45.360 --> 00:01:49.370
Art: The test program for the observatory is pretty rigorous and that's because

28
00:01:49.390 --> 00:01:53.380
once we get into space, we have only one shot at this.

29
00:01:53.400 --> 00:01:57.450
Candace: The next thing we do is make sure that everything's still

30
00:01:57.470 --> 00:02:01.480
working after the full suite of environmental tests.

31
00:02:01.500 --> 00:02:05.540
So we do deployments of the solar arrays and the

32
00:02:05.560 --> 00:02:09.650
GMI and the High Gain to make sure those still work just the same way they

33
00:02:09.670 --> 00:02:13.690
did before we went into environments.
Art: The GPM Observatory

34
00:02:13.710 --> 00:02:17.760
is about 3900 kilogram spacecraft, fully loaded.

35
00:02:17.780 --> 00:02:21.790
Very large spacecraft. And the larger the satellite is,

36
00:02:21.810 --> 00:02:25.830
just the logistics of moving them from one location

37
00:02:25.850 --> 00:02:29.840
to another is much more complicated than when you're dealing with

38
00:02:29.860 --> 00:02:33.880
a small satellite. That's why spacecrafts or

39
00:02:33.900 --> 00:02:37.990
observatories like GPM Core Observatory take longer

40
00:02:38.010 --> 00:02:42.110
for us to complete the manufacturing and testing

41
00:02:42.130 --> 00:02:46.170
and all the environmental testing we need to do at the end.

42
00:02:46.190 --> 00:02:50.310
Candace: Here at Goddard we have about 300 people working on GPM.

43
00:02:50.330 --> 00:02:54.360
About 100 civil servants and about 200 contractors.

44
00:02:54.380 --> 00:02:58.470
That, in addition to a number of people at the Japan

45
00:02:58.490 --> 00:03:02.510
Aerospace Exploration Agency who worked on the DPR instrument

46
00:03:02.530 --> 00:03:06.540
and at Ball Aerospace who worked on the GPM Microwave Imager

47
00:03:06.560 --> 00:03:10.580
instrument.
Art: Once we complete the GPM Core

48
00:03:10.600 --> 00:03:14.600
Observatory testing inside our high bay,

49
00:03:14.620 --> 00:03:18.630
we get the spacecraft prepared for shipment. Then our next step

50
00:03:18.650 --> 00:03:22.780
is to transport it to Andrews Air Force Base and install it

51
00:03:22.800 --> 00:03:26.840
on the C-5 and then take it to Tanegashima Island.

52
00:03:26.860 --> 00:03:30.880


53
00:03:30.900 --> 00:03:34.920
[rain falling]

54
00:03:34.940 --> 00:03:39.040


55
00:03:39.060 --> 00:03:43.040


56
00:03:43.060 --> 00:03:43.837


